Construction Update October 2023

037_SEP'23

We’ve welcomed the sun after a cold winter and have been pushing forward with construction.

Earthworks is substantially complete with both stormwater and sewer services 95% complete in Stage 1.  The stormwater connection under Yass Valley Way through to the pond is currently being programmed and we will advise of any traffic disruptions once the timing has been confirmed.  When this work is complete the landscaping along the southern side of Yass Valley Way will commence.  Roads and kerb throughout stage 1 are scheduled for commencement in November.

There has unfortunately been some delays due to infrastructure requirements and procurement timeframes.  This has impacted the construction program and subsequent completion timing.  Practical completion is now anticipated to be in early 2024 with settlements expected to occur around April/May 2024.

If you have any questions or would like more information – please email info@hamiltonriseyass.com.au

Thankyou

The Hamilton Rise Team

You Might Also Like

Construction Update March 2024

After the stormy weather during the Christmas and January periods which required some restoration works, we’re pleased to advise that construction is progressing well within

Landscaping & Traffic News August 2023

Construction at Hamilton Rise is coming along well and we’re thrilled to advise we will be commencing our entry landscaping due to required stormwater infrastructure.

Construction Update July 2023

Good Afternoon, Earthworks are continuing in stage 1, with the recent inclement weather causing a few minor delays and completion now anticipated by mid July. These delays