Construction Update Feb 2022

Welcome to our inaugural Construction Update for Hamilton Rise.

After selling out of Stage 1 in December last year we have been busy finalising engineering details and procuring contractors so we can get construction underway as soon as possible.

Our civil works on stage 1, which comprises 49 residential blocks and 1 multi unit block, will be undertaken by RAM Constructions.  This stage of works will include:

  • Bulk earthworks across the stage;
  • Servicing (water, sewer, electricity, NBN etc);
  • Roads and pavement; and
  • Landscaping

We’ve been working closely with Yass Valley Council and anticipate receiving our Construction Certificate over the course of the next month, with site establishment and civil commencement to follow shortly thereafter.

Completion of stage 1 is anticipated for late this year with this timing of course subject to weather!

On the sales front – we are hoping to release the next stage of residential land mid year.  Keep an eye on your inbox for more details!

If you have any questions or queries, please drop us an email at info@hamiltonriseyass.com.au

Have a great day!

You Might Also Like

We’re REGISTERED

STAGE 1 – NOW REGISTERED!!! It’s been a journey, but we’re so thrilled to advise Stage 1 at Hamilton Rise is now registered and ready

Construction Update March 2025

STAGE 1 CONSTRUCTION IS COMPLETE! We have reached physical completion of ALL WORKS within Stage 1 at Hamilton Rise.  Yass Valley Council have attended the