Construction Update April 2023

Construction Update april 2023

Good Afternoon,

The Civil works on Stage 1 have progressed well during the first few months of 2023, given the dry weather over the Christmas period coupled with a real push by the team to get traction. 

Currently, all of the bulk earthworks for this stage are very close to complete and you can see the roads have taken shape!

The civil team are now onto the construction of hydraulics which include services such as sewer, water and stormwater.  We are hoping to have this section of works complete over the next few months – weather pending. 


We hope you all have a wonderful Easter and a very happy and safe holiday period!

As always if you have any questions or queries, please drop us an email at info@hamiltonriseyass.com.au

Have a great day!

You Might Also Like

We’re REGISTERED

STAGE 1 – NOW REGISTERED!!! It’s been a journey, but we’re so thrilled to advise Stage 1 at Hamilton Rise is now registered and ready

Construction Update March 2025

STAGE 1 CONSTRUCTION IS COMPLETE! We have reached physical completion of ALL WORKS within Stage 1 at Hamilton Rise.  Yass Valley Council have attended the